Lamers System Care mounts SMART FLOW on the dry side, on cooler covers, inlets and sea chest walls, and the system remains fully accessible from the engine room, so the ultrasonic part of a sea chest upgrade is not itself dry-dock work. Changes to the outside of a sea chest while the ship is afloat, such as new openings or valves, are carried out by specialist diving contractors using cofferdams or blanking plates; this is work that Lamers System Care does not do itself.
Core answer
Afloat sea chest work follows a standard sequence:
- A cofferdam or blank is fitted over the opening on the hull, so the area inside can be worked on dry.
- Owner, class and contractor agree a repair or installation plan. One contractor describes engineered cofferdams used “without the need for costly drydock delays”.
- US Coast Guard guidance on underwater surveys (NVIC 1-89) lists means of blanking sea chests, for example to remove sea valves, and hinged or removable grates for access.
One contractor says it fits additional sea chests afloat for scrubber intakes and outlets “by installing a cofferdam on the hull” (project page). Another offers this at lay berths where dry docking is “not available, expensive or time consuming” (service page).
What this question asks
| Method (labelled source) | What it allows afloat |
|---|---|
| Cofferdam on hull (Hydrex; Subsea Global Solutions) | New sea chests, scrubber intakes/outlets, repairs |
| Diver-fitted blanking (FN Diving) | Work on sea chest plating, valves, box coolers and anodes |
| Blanking per USCG NVIC 1-89 | Removal of sea valves during underwater survey |
How Lamers System Care handles this
SMART FLOW should start on a clean cooler. In the LSC fishing-vessel case (pdf), the cooler protected from a clean start was still largely clean after 31 months. Lamers System Care therefore plans installation for the moment the coolers are clean. Plan it via lscare.nl.